Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


William S
2019-04-25T18:39:30Z
When Running a job the Result column will show Running and the Status column will show Running - 0%.
If I stop the job and then run it again, the status will show Running with an incremental percentage that goes to 99%.
Why does the job show 0% the first time running it?
Sponsor
Forum information
Support
2019-04-30T08:13:56Z
The %-column is depending on the last execution time. So, for example if last execution time was 1 hour you will see it in 0% for a long time. First time it goes up from 0 to 99 in one minute because it has no idea how long time it will run. Next run is based on last run.
Henrik
Support
http://www.visualcron.com 
Please like  VisualCron on facebook!
William S
2019-05-02T18:16:19Z
Thank you. That is logical.