Has anyone see a job disappear? We have a job that runs on the first day of every month in the morning and I was notified it did not create the report for October 1. I looked and saw that the report was created on September 1 just fine. When I logged into VisualCron the job was no longer there.
My first reaction was that someone accidentally deleted the job so I used a program to search through the VisualCron log files in the "c:\Program Files\VisualCron 4\log\" folder. It didn't come up with any results for the deletion. I then searched for the key phrase "Deleted Job" and it still did not give any results. This job was not updated and I'm very confused at this point. Here are the results when I search for the job name:
2/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
2/1/2009 9:40:41 AM Info Job completed: AMCR - Batch Tracks
3/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
3/1/2009 9:40:42 AM Info Job completed: AMCR - Batch Tracks
4/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
4/1/2009 9:42:50 AM Info Job completed: AMCR - Batch Tracks
5/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
5/1/2009 9:47:56 AM Info Job completed: AMCR - Batch Tracks
6/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
6/1/2009 9:46:56 AM Info Job completed: AMCR - Batch Tracks
7/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
7/1/2009 9:46:50 AM Info Job completed: AMCR - Batch Tracks
8/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
8/1/2009 9:41:03 AM Info Job completed: AMCR - Batch Tracks
9/1/2009 9:40:00 AM Info Job started: AMCR - Batch Tracks
9/1/2009 9:41:31 AM Info Job completed: AMCR - Batch Tracks
Does anyone have ideas on what may have happened here? I have created the job again however if someone has seen this before please let me know what you found! The version I am using is 4.9.37.
Regards,
Peter