Hi VisualCron,
Quick question that seems easy but I'm stuck.

Assume I've got 20 tasks in 1 job. All tasks run at once (Run Tasks In Order is unchecked). I'd like to re-run task number 20, either when the whole job is complete, or after each of tasks 1-19 are complete. (#20 is a Powershell task, if it matters)

I tried Task Flow, thinking I could have tasks 1 through 19 each trigger #20 using "Go to Task" but it doesn't appear to be triggering. Is this because I'm not running the tasks in order?

I'd like to keep task #20 inside the existing job instead of making its own job. Of course, the easy way would be a separate job, and Job Flow, but if there's any way to do one of the other options above I'd like to explore it.

Any clues what I'm doing wrong?

Thanks!
Sponsor
Forum information
Support
2014-04-21T09:19:02Z
In this case you need to separate it. I recommend a new Job where you use the Job completed Trigger to watch that first Job.