Dear Visualcron Team,

first of all i wanted to say thanks for your awesome tool !

My request/question, we generate alot of reports at the last workday of the month (Ultimo), which need to be processed quite fast afterwards.

Is there an option / upcoming feature which would allow us to use a "last workday of the month" trigger ?

best regards
SPIEDV
Sponsor
Forum information
ErikC
2010-10-14T13:51:24Z
Hi Spiedv,

In te version 5.6.9 there is a last workday of the month trigger.
You have to select specific days of the motnh, and in the dropdown, select 'Last' workday.
This is however above the 1st workday item, so you might have missed it.

Regards,
Erik