Hi - i am running an upgrade project for my firm's VC servers. We have 4 multi server environments all running v8.3.5. Some users require access to all environments.

During the upgrade to v9.8.0, as soon as I start to upgrade servers, the users will need to upgrade client also to access the upgraded server (no backward compatibility). Once they upgrade they will no longer be able to the access the other servers.

If i upgrade this way it squeezes the time I have to get users to test and sign off their jobs.

The users could go thru the inconvenience of upgrading client then downgrading after testing.

But i want to know if it is possible to run 2 different version clients on one desktop (I have not tested this yet).

Anyone done this - will it work? What is the process?

Thanks in advance for any replies!
Simon
Sponsor
Forum information
Support
2021-07-23T08:49:56Z
Originally Posted by: Ibbo 

Hi - i am running an upgrade project for my firm's VC servers. We have 4 multi server environments all running v8.3.5. Some users require access to all environments.

During the upgrade to v9.8.0, as soon as I start to upgrade servers, the users will need to upgrade client also to access the upgraded server (no backward compatibility). Once they upgrade they will no longer be able to the access the other servers.

If i upgrade this way it squeezes the time I have to get users to test and sign off their jobs.

The users could go thru the inconvenience of upgrading client then downgrading after testing.

But i want to know if it is possible to run 2 different version clients on one desktop (I have not tested this yet).

Anyone done this - will it work? What is the process?

Thanks in advance for any replies!
Simon



It can cause issues, we strongly advise against it
Michael
Support
http://www.visualcron.com 

Please like  VisualCron on facebook!
jdykhuis
2021-10-14T15:25:06Z
What is the recommended process to follow when upgrading? Users need to be able to test the new version on Pre-Prod while still using the current version on Prod? Also, the Prod Upgrade is more difficult if the clients all need to be upgraded at the same time.