This is already fixed in 8.2.9. If you want to test it out please go to: https://www.visualcron.c....aspx?g=posts&t=7498
It would be great if you could verify that it works for you.
Hi,
I'll ask my operations team to run some test with version 8.29. I'll leave my feedback after they complete their tests. Thank you.
Thanks!
Hi,
Unfortunately I have bad news to report. The problem persists. Job will show a status of Running with the Hourglass image even though the job has completed.
Also there is a new behavior, the screen (VisualCron client) will "black out" for a fraction of a second as if the screen is attempting to refresh. It doesn't happen all the time.
Sorry, forgot to state my test parameters.
8.29 client connecting locally to a 8.29 server
8.29 client connecting remotely to a 8.28 server
and
With a 8.29 client connecting locally to a 8.29 server, and also connecting to two 8.28 servers at the same time.
It appears, whenever the 8.29 client is used to connect to a 8.28 server, the problem exhibits itself. I say, it "appears" because I only have 5 test jobs on the a 8.29 server. The two 8.28 servers have a combined total of 225 jobs.
I'm hoping the answer is, the fix was at the server level and not at the client. Which would lend itself to why the 8.29 client connecting to a 8.28 server, the problem persists.