Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


silviom
2009-04-17T16:52:46Z
Hi, we are using VC 4.9.40, yesterday the machine which holds the VC Server was shutdown, after that I noticed that the next run times were changed back to past time.

The rare thing is that the main view shows past time "next run" and when the task properties dialog is open the right "next run time" is shown. If i make no changes and press "OK" in edit task dialog the main view "next run time" gets updated (see screenshot bellow).

If the main view "next run time" is not updated (manually or doing the above "edit task" procedure) then the tasks doesn't run anymore.


UserPostedImage


Sponsor
Forum information
Support
2009-04-17T16:55:09Z
Does it update when turning the Server Off and then On?
Henrik
Support
http://www.visualcron.com 
Please like  VisualCron on facebook!
silviom
2009-04-17T17:31:47Z
Yes, turning VC server off and on again has updated all the "next run times" to the correct ones.