Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


stevja01
2015-07-21T15:29:20Z
We have a service which has several JOBs which run all tasks at the same time. Once all those tasks complete then we have a FLOW setup to trigger another JOB. To reduce our maintenance effort for this service, I was wondering if there was a way to do this? Identify to VisualCron that tasks 1-X should run at the same time, but that task Y should run once tasks 1-X complete in the SAME job. Is that possible?
Sponsor
Forum information
thomas
2015-07-22T06:42:29Z
Not sure if I understood you 100%, but I think I asked a similar question a few weeks ago. If you are asking wether one can mix synchronous tasks with async taks in the same job, the answer is no I believe. You have to split up into separate jobs

Thomas
Scroll to Top