Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


osirisja
2013-09-05T10:24:01Z
Hi Henrik

The latest update (7.05) which allows activation of triggers is a very useful addition for me so thanks for that.

In order to support this feature, I was running the VC Report task to show Active/Inactive Triggers and while it displays the 'Next Run' column for all jobs, the values are not consistent with what is shown in the Client.

In the attached screenshots you can see the Client shows a description of the Trigger state in the column 'Next Run', however in the report it shows a Date/Time stamp, which is largely irrelevant for an event trigger.

Would it be possible to either add the same description in the report as in the Client, or perhaps even add a new column which can show the actual Trigger state, especially if it has failed?

Cheers

Andy

osirisja attached the following image(s):
Sponsor
Forum information
Support
2013-09-05T12:34:31Z
Thanks, we have added this for next version.
Henrik