Job retriggering after task update - VisualCron - Forum

Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


hjohnson
5 years ago
We have a job that can only run once a day. On occasion an adjustment needs to be made, but the job should not run after that adjustment. It should wait until the next file is uploaded, usually the next day. Is there a way to set a dependency or condition to not run if the job has already ran for the day? We are not allowed to delete the files off of the SFTP site that we are triggering from.
Sponsor
Forum information
thomas
5 years ago
What are you adjusting when you make an adjustment? The trigger itself? If so, maybe this setting is relevant:

Capture.PNG
hjohnson
5 years ago
not usually. This time I was reactivating a task that had been shut off the previous day.
Support
5 years ago
Originally Posted by: hjohnson 

not usually. This time I was reactivating a task that had been shut off the previous day.



You could set up a condition or a Flow to check if a file exists before the job runs
Michael
Support
http://www.visualcron.com 

Please like  VisualCron on facebook!
hjohnson
5 years ago
we don't delete it off of the FTP server that we check. So, there will always be a file that exists.