Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


clausbmayer
2011-12-14T09:51:08Z
Hi everybody,

we have the effect, that certain jobs start all the sudden without hitting the trigger.
The Log says, that 'admin ran the job manually', what we do not understand.

There are only a few jobs affected, but these few jobs do start each day at a different time and outside their trigger-times. When they reach trigger-time, they start again.

Has anybody else experienced similar behaviour?

Kind regards,

Claus


Sponsor
Forum information
Support
2011-12-14T09:53:13Z
Hi Claus,

please upgrade to latest version and turn on extended debugging in server settings->log. Then email us the log after you have received a run that was not planned.
Henrik
Support
http://www.visualcron.com 